Flagler County Aircraft Hangar

Background:

Flagler County’s Mosquito Control Division needed an aircraft hangar constructed on their property in Palm Coast, FL. During project construction, a soil investigation revealed a layer of organic debris between two layers of dense sand.

The Problem:

In order to adequately support the aircraft hangar, the crew needed to install a deep foundation to transfer the building loads below this organic layer. Ultimately, the foundation would support compressive loads on the order of 24 kips and tensile loads of 10 kips.

The Solution:

CHANCE® helical combo piles were chosen as the deep foundation option. The combo pile utilizes a square shaft lead section and round shaft plain extensions. The square shaft offers excellent penetration, and the round shaft extensions provide greater lateral resistance through the soft organic layer, as the surface area of the round shaft is greater than that of the square.

The contractor installed a total of 112 piles in one 40-hour work week. Each pile was installed to support 24 kips in compression and 10 kips in tension with a safety factor of two. Two tension and two compression load tests were conducted prior to production pile installation. The CHANCE® combo piles were configured with a triple helix 8”/10”/12” SS5 (1-1/2” X 1-1/2” square) lead section and RS2875.203 (2-7/8” round shaft) plain extensions. The piles were equipped with a 7”x7”x0.5” square new construction plate to allow for connection to the poured concrete footings.

CHANCE Helical Underpinning

Square shaft lead section installation (back left) Round shaft extension bolted to lead section (right) Square shaft to round shaft transition fitting (front left)

 

CHANCE Helical Underpinning

Square shaft to round connection

 

CHANCE Helical Underpinning

New Construction Plates installed to allow for pile and footing connection

 

CHANCE Helical Underpinning

Compression Test

 

CHANCE Helical Underpinning

Tension Test

Key Benefits:

  • Time to install faster than concrete

  • Standard equipment for installation
  • Labor savings - smaller crews
  • Immediate proof testing and loading
  • Reach competent soil below active zone
  • Low to no vibration/noise